The new ICC Arbitration Rules

As Richard Smellie explains, the ICC International Court of Arbitration has revised its Arbitration Rules. The present Rules were published in 1998. The new Rules come into effect from 1 January 2012 . Unless an existing ICC arbitration clause calls for the application of the ICC rules as at the date of the contract, the new Rules will apply to any arbitration commenced after 1 January 2012.

The ICC International Court of Arbitration is now arguably the dominant source of administered arbitration, and a core business for the International Chamber of Commerce. The new Rules are an update, and in a number of respects set out the practice developed by the Court over the past 10 years, providing transparency and greater certainty, particularly in relation to multi-party arbitration, consolidation and jurisdictional challenge.

A number of the changes are updates: the Chairman of the Tribunal is now the President, references to telex have been replaced with email, and the rules are said to cover simply “disputes” rather than “business disputes” so that there is no suggestion that disputes involving States are somehow excluded. The early quantification of claims in the Request for Arbitration is now encouraged by Article 4(3)(d), and Article 11 now requires arbitrators to be impartial, and to confirm their impartiality (it having been previously assumed that “impartiality” was covered by the confirmation of “independence”). Further, by Article 13, where the Court does not accept the proposal of a National Committee, or one party is a State, or the President of the Court considers it necessary, then the Court now has the power to appoint as arbitrator any person it considers suitable.

The much debated topic of confidentiality has also been addressed. Contrary to the understanding of many users of international arbitration, it is not automatically confidential. The new ICC Rules do not change that for ICC-administered arbitration, but expressly provide at Article 22 (3) that the Tribunal may, upon the request of the parties, make orders concerning the confidentiality of the arbitration.

The most significant changes are in three areas: case management (which the rules require and actively encourage), interim and conservatory measures (where the ICC has introduced an Emergency Arbitrator procedure) and multi-party disputes (which are now provided for, the practice of the Court having been enshrined in the Rules).

Case management

The 1998 Rules called for the arbitration to be complete within 6 months, and the practice has been that the Court will approve extensions to that time frame as needed (and extensions have usually been needed). Under the new Rules, Article 22 now includes an express obligation on the parties (as well as the Tribunal) to make every effort to conduct the arbitration “in an expeditious and cost effective manner”, (Article 22(1))and at 22(2) obliges the Tribunal to adopt measures to ensure effective case management (provided any such measures are not contrary to any agreement of the parties).

Article 24 and Appendix IV are entirely new. Article 24 requires the Tribunal to call a Case Management Conference, at the outset of the proceedings, when the Terms of Reference are drawn up (this being a particular feature of ICC arbitration: it is the first task of the Tribunal following receipt of the file from the Court), or immediately thereafter. The objective – and indeed obligation – is to consult with the parties on procedural measures that might be adopted pursuant to Article 22(2) “to ensure effective case management”.

In order to further encourage case management, Article 24 calls on the Tribunal to hold subsequent “Case Management Conferences” to ensure continued effective case management’, and at 24(4) the Tribunal is empowered to request the attendance of a party representative at a Case Management Conference, the intention being to secure the party’s “buy in” to effective case management procedures.

Appendix IV provides examples of case management techniques that might be adopted. None of the proposals in this appendix are in themselves radical, but the appendix provides a useful list of possible case management techniques. The list includes various proposals aimed at limiting disclosure, and looking for areas where the parties or their experts might agree, limiting the length of written submissions and evidence, and looking at bifurcation, the use of IT, and giving consideration to whether there are issues that might be decided on a documents only basis. It also includes encouragement to the parties to consider settlement.

The case management provisions conclude at Article 27, where a new obligation is placed upon the Tribunal: at the conclusion of the proceedings, when the Tribunal declares the proceedings closed, the Tribunal must now also inform the Secretariat and the parties of the date by which the Tribunal expects to submit its draft award to the Court for approval.

Emergency Arbitrator

Whilst the 1998 Rules made provision for the issue of interim or conservatory measures by the Tribunal once established, they did not provide a mechanism for urgent application pending the Tribunal being constituted. Consequently parties with an ICC arbitration clause would have to look to local courts for any urgent interim or conservatory measures, or wait for the Tribunal to be constituted – a process that could take several months.

The new Rules, however, now provide, at Article 29 and Appendix 5, for the appointment of an Emergency Arbitrator to make orders for urgent interim or conservatory measures, a procedure that has been included in a number of other administered arbitral rules (the SIAC and Stockholm rules being examples).

Appointment of the Emergency Arbitrator is made upon request to the Secretariat (Article 29(1)). The request must be made before the transmission of the file to the Tribunal if a Request for Arbitration has already been lodged. The appointment is made by the President of the ICC Court, who also decides whether the emergency provisions apply. Further, the fee ($40,000) must be paid before the application will be notified to the parties under Appendix IV Article 2, and the emergency procedure commenced.

The Emergency Arbitrator must act fairly and impartially, and allow each party reasonable opportunity to present its case (Appendix IV, Article 5 (2)). By Appendix IV, Article 6(4) the Emergency Arbitrator must send his order to the parties within 15 days from the date the file is transmitted to him, and the date of transmission is expected to be on the Emergency Arbitrator’s appointment, which should be within two days of the request for the appointment having been made (2(1)).

If a Request for Arbitration has not already been made by the party seeking the urgent interim relief, that Request must be made within 10 days of making application, failing which the President must terminate the emergency proceedings (Appendix IV, Article 1 (6)).

It is important to note that by Article 29(2), the Emergency Arbitrator’s decision takes the form of an order, and not an award, and by Article 29(3) does not bind the Tribunal ultimately established to resolve the dispute. It is not therefore in the nature of a final, binding decision of an arbitrator, with the result that it is unlikely to be enforceable as an arbitrator’s award. Its “teeth”, however, are found in the power given at Article 29(4) to the Tribunal appointed to determine the dispute, to decide upon any claims relating to the emergency arbitrator proceedings. Noncompliance with an Emergency Arbitrator’s order could, therefore, result in a claim.

It is also important to note that the parties are expressly given the option to opt out of these provisions. As arbitration is a process born of contract, parties could, by agreement, say that any particular parts of the Rules do not apply, but if that included rules which the ICC Court considers fundamental to ICC arbitration, then the ICC Court would decline to administer the arbitration. Whether the emergency arbitrator procedure might be regarded as fundamental is not known, but the parties have been given the express right to opt out should they so choose.

Further, by Article 29(6), these provisions will not apply to arbitration agreements entered into before 1 January 2012, and by Article 29(7), it is not intended to prevent a party applying to local courts for interim or conservatory relief.

Multi party disputes/multiple contracts

For the first time, the ICC Rules now include provision for multi-party disputes and multiple-contract arbitrations. These are found at Articles 7, 8 and 9, with Article 6 (Effect of the arbitration agreement) and Article 10 (Consolidation of arbitrations) having been amended to take account of the new multi-party provisions.

It is important to note that these provisions do not answer whether a party might be joined and/or whether all disputes referred might be heard in a single arbitration. Rather, they set out a framework for the resolution of these issues. The framework reflects the present practice of the ICC Court.

Article 6 now gives the Court the power to make a prima facie decision where a proposed Respondent raises an issue as to whether all of the claims made in an arbitration can be heard in a single arbitration. If the matter is referred to the Court by the Secretary General, to allow the arbitration to proceed the Court must be satisfied that, for multi-parties, there is prima facie arbitration agreement under the ICC Rules that binds all of the parties, and for multiple contracts, that there are prima facie compatible arbitration agreements and that all parties have agreed that the claims can be determined together in a single arbitration.

Any decision of the Court remains subject to the decision of the Tribunal. For the joinder of additional parties (Article 7), the Request for Arbitration against the additional party must be made before the confirmation or appointment of any of the arbitrators (unless the parties agree otherwise), and the request must include information concerning the arbitration agreement relied upon, and, if there is more than one arbitration agreement, the arbitration agreement relied upon for each claim made.

A party so joined files an Answer, and may bring a cross-claim against any party in the arbitration. By Article 8 however, like the Request that joined this party, where it makes a cross-claim its Answer must include information concerning the arbitration agreement relied upon, and if there is more than one arbitration agreement, the arbitration agreement relied upon for each claim made.

Through this procedure therefore, any party that is joined is given opportunity to play a part in the constitution of the Tribunal, and to raise any jurisdictional objection from the outset. Further, and importantly, the Tribunal is provided with the basic information it will need where there is an issue as to jurisdiction.

Article 9 supplements these provisions, by confirming that subject to the Court allowing the arbitration to proceed under Article 6, claims arising from more than one contract can be brought in a single arbitration. This does not however impinge on the Tribunal’s authority to determine any jurisdictional issue that might be raised.

Finally, by Article 10, the Court is now empowered to consolidate arbitrations where claims are made under more than one arbitration agreement, and the disputes arise in connection with the same legal relationship, and where the Court finds that the arbitration agreements are compatible.

Conclusion

The new ICC Rules are to be welcomed. They bring the ICC Rules up to date, and into line with modern practice and expectations. There will inevitably be some uncertainty as to how some of the more complex provisions concerning emergency arbitrators and multi-party disputes will work, but the new Rules have been carefully thought through and drafted, and appear fit for purpose.

Notes:
1. A copy of the new rules can currently be downloaded from the ICC website - www.iccwbo.org.

Back to the previous page | Next article