By: Ben Smith , Partner; Huw Wilkins , Partner; and Jonathan Clarke ,
Associate
In a much-anticipated judgment that was released at 10:30 a.m. on 1 April
2026, the TCC brought a touch of seriousness to April Fools’ Day
morning.
Mr Justice Constable’s decision to grant a building liability order
(“BLO”) in
Crest Nicholson Regeneration Ltd & Ors v Ardmore Construction Ltd
(In Administration) & Ors
[2026] EWHC 789 (TCC) is already being viewed as one of the most significant
developments to the Building Safety Act 2022
(“BSA”) regime to date.
Our initial thoughts on Mr Justice Constable’s decision are summarised
below.
Key Takeaways
Significantly, Mr Justice Constable decided that:
-
a BLO can be granted before any finding of relevant liability –
what is being referred to as an “anticipatory” BLO;
-
an adjudicator’s decision, even though it is only temporarily
binding, can amount to a relevant liability under section 130 of the
BSA;
-
a court can order a BLO in respect of a proportion of a relevant
liability under section 130(2) of the BSA rather than its entirety,
should it be just and equitable to do so; and
-
deliberate corporate restructuring will not mitigate statutory liability
of associated companies, even where shares are vested in a family trust
via a holding company (such as in the case of the Sixth Defendant here).
Helpful commentary has also been provided on:
-
the various applicable principles for a BLO, in light of the developing
case law and statutory regime;
and
-
the persuasiveness (or lack thereof) of various arguments as to why it
may not be just and equitable to grant a BLO.
Facts
The claimants were members of the Crest Nicholson Group, including Crest
Nicholson Regeneration Limited which was the developer and Crest Nicholson
(South) Limited which is the long leaseholder of 19 residential apartment
buildings in a development known as Admiralty Quarter in Portsmouth (the
“Development”). The four Crest Nicholson
entities noted as claimants in the judgment are collectively referred to as
“Crest”.
Ardmore Construction Limited (“ACL”) was the
main contractor for the Development under an amended 1998 JCT D&B
Contract.
Following investigations by Crest, it was alleged that the external wall
systems at the Development were defective because of certain fire safety
defects – principally (i) the presence of combustible polyethylene
(“PE”) cladding panels and (ii) fire barriers
were missing or inadequate. Other internal fire safety defects, including
defective fire doors and inadequate compartmentation were also observed.
Crest started an adjudication for the costs associated with the anticipated
remedial works for the non-compliant elements of the external wall systems.
The adjudicator decided that the defects amounted to a breach of Part B of
the Building Regulations and ACL’s duties under the Defective Premises
Act 1972 (the “DPA”). Consequently, the
adjudicator determined that ACL should pay Crest approximately £14.9
million.
Around the same time as the adjudicator’s decision, ACL went into
administration. The sums awarded by the adjudicator were not paid. Crest
therefore made an application to the court for two forms of relief against
the Fourth to Tenth Defendants (collectively the “Ardmore Group Companies”):
-
An “anticipatory” BLO: An order
that any liability which ACL might ultimately be found to owe under
section 1 of the DPA or as a result of a building safety risk would also
be the joint and several liability of the associated Ardmore Group
Companies, even though final liability had not yet been determined.
-
An “adjudication” BLO: An order
making the same associated Ardmore Group Companies jointly and severally
liable for the £14.9 million awarded in the adjudicator’s
decision, which had gone unpaid following ACL’s administration.
The Ardmore Group Companies resisted both aspects of the application. Unlike
in the last successful BLO application in
381 Southwark Park Road RTM Co Ltd v Click St Andrews Ltd (In
Liquidation)
[2024] EWHC 3569 (TCC), the Ardmore
Group Companies decided to actively participate in the BLO hearing.
Crest’s arguments
Crest’s position was that:
-
without a BLO, any judgment or adjudication award against ACL would be
unenforceable;
-
the Ardmore Group Companies had deliberately tried to structure its
affairs to shield itself from liability under the BSA and the DPA;
-
an “anticipatory” BLO would provide commercial
clarity and procedural efficiency; and
-
an “adjudication” BLO was reasonable as the
adjudicator’s decision represented a relevant liability arising
from building safety risks.
The Ardmore Group Companies’ arguments
The Ardmore Group Companies’ position was that:
-
the application was premature, given that liability and quantum had not
been finally determined;
-
Crest was a sophisticated commercial party, whereas the financial impact
on the Ardmore Group Companies made a BLO unjust; and
-
an adjudication decision was only temporarily binding and amounted to
“rough justice” and was never intended by the BSA
to be a relevant liability.
Mr Justice Constable’s summary of the key principles for a
BLO
Before turning to the issues, Mr Justice Constable distilled the authorities
and other material referred to the court on the topic of BLOs as follows:
-
the assessment of whether it is just and equitable to grant a BLO is a
broad test and necessarily fact specific;
-
the court’s power is discretionary and should therefore be
exercised having regard to the purpose of the BSA and all relevant
factors;
-
the court’s power includes the ability to make an anticipatory
BLO, that is a BLO which is ordered before a finding of any relevant
liability;
-
the purpose of section 130 of the BSA is to provide the court with
powers to allow those directly responsible for defective work which
gives rise to a relevant liability to be pursued through their
associates. The purpose of the BSA should not be defined as in any way
limited to being directed at special purpose vehicles and shell
companies;
-
the court should not seek to limit the statutory test by setting out an
exhaustive list of factors;
-
it will generally be sensible for an application for a BLO to be case
managed within the same proceedings as the main claim; and
-
whether an application for a BLO should be determined in advance of, as
part of, or indeed after, the liability hearing in the main claim will
be a matter of case management. Ultimately, whenever the application is
heard, the primary consideration for granting a BLO is whether it is
just and equitable to do so.
The decision
Applying those principles, the court granted both the
“anticipatory” BLO and the
“adjudication” BLO. Mr Justice Constable decided that:
-
an adjudicator’s decision could give rise to a relevant liability
for the purposes of section 130(3) of the BSA. Mr Justice Constable
rejected the Ardmore Group Companies’ argument that a court must
itself be satisfied that there is a relevant liability before it can
make a BLO. It was held that an adjudicator’s decision is binding
unless successfully challenged and there was nothing to suggest that the
statutory regimes for adjudication and BLOs could not operate together;
and
-
it was just and equitable to grant the anticipatory BLO because the
Development clearly contained building safety risks for which ACL would
likely be found liable. It was appropriate to grant the BLO because it
had been conceded that a number of the Ardmore Group Companies were
“associates” of ACL for the purposes of section
131. It was also noted that ACL had been placed into administration for
the benefit of the wider group, with the arguable purpose of avoiding
liabilities under the BSA.
Conclusion
This case is a significant development on the last (and first) successful
BLO granted in
381 Southwark Park Road RTM Co Ltd v Click St Andrews Ltd [2024]
EWHC 3569 (TCC). In his decision here, Mr Justice Constable grappled with
many of the key issues relevant to the BLO regime. He considered the
potential scope of BLOs and how they can be utilised by parties looking to
enforce DPA/building safety liabilities whilst reinforcing that the
assessment of whether it is just and equitable to grant a BLO is a broad
test and necessarily fact specific.
However, we understand that Ardmore is preparing to appeal the decision and
that the Court of Appeal may soon have its first opportunity to consider
these important issues.