Lloyd Projects Limited v John Malnick

Friday, 22 July 2005

Key terms: 
Enforcement - Section 107(2) - “in writing” - material terms - oral agreement - scope - quality - standard of work.

Mr Malnick converted his former offices in Islington into 3 residential units. The claimant carried out the construction work. An oral agreement was reached on 3 September for the builder to carry out the conversion work. A manuscript note of the telephone conversation recorded the price at £412,000 inclusive of VAT with no extras. The work commenced on or around 12 September 2003. Shortly afterwards the parties agreed a variation of £10,000.

On 11 February 2004, the contractor wrote to Mr Malnick setting out his understanding of the terms of the contract. A response of 17 February 2004 identified that there were some differences in the understanding in terms of the quality of the work, the scope of the work (did the additional £10,000 relate solely to the chimney work, or did it cover the additional pointing and the drainage work), and whether the PC sum for the kitchen and bathroom fittings was a maximum price that was not to be exceeded or whether the actual cost was to be paid to the builder.

Disputes arose in connection with these items and others. The dispute was referred to adjudication. The claimant sought to enforce the Adjudicator’s decision.

The issue was whether the letters of 11 and 17 February 2004 were sufficient evidence in writing of the agreed terms pursuant to Section 107(2)(b) or (c) of the HGCRA. The defendant argued that not all of the material terms had been recorded in the documents. Further, the letters were some 5 months after the work had started and demonstrated that the parties had a different understanding of the agreement.

HHJ Kirkham said that whether the Adjudicator felt able to deal with the claim was irrelevant; what mattered was objectively whether the material terms had been recorded in writing. The contract had formed orally on 3 September 2004. The question was whether that contract was sufficiently recorded in writing. Her Honour referred to Ward LJ in RJT who said that “what has to be evidenced in writing is, literally, the agreement, which means all of it, not part of it.” In addition, the decision of Jackson J who in Stratfield Saye considered that all of the expressed terms needed to be recorded in writing. This meant all of the material terms.

Her Honour held that it was clear from the documents that the scope of the work to be carried out for the sum of £10,000, and whether the PC sum for the kitchen and bathroom fittings were the maximum amount or whether the builder was to be paid the actual cost were material to the parties, and had not been adequately recorded in writing at the time that the oral contract was made. The agreement was therefore not adequately recorded in writing for the purposes of Section 107(2)(b) and (c) and Her Honour refused to enforce the decision.

Key contact

Tel: +44 (0)20 7421 1986
Tel: +44 (0)20 7421 1986