L Brown & Sons Limited -v- Crosby Homes (North West) Limited

Case reference: 
[2005] EWHC 3503 (TCC)
Monday, 5 December 2005

Key terms: 
Adjudicator's Decision - Enforcement - JCT Standard Form of Building Contract with Contractor's Design - Under and in connection with - Side Agreements - Construction Contract - in writing - applicability of dispute resolution clause in main agreement

The parties entered into a JCT With Contractor's Design a contract for the construction of 114 residential apartments in Manchester. This case concerns the enforcement of an Adjudicator's decision. During the adjudication, Crosby Homes raised three jurisdictional challenges:
  1. There was no jurisdiction under the "side agreements";
  2. If there was an agreement it was not in writing; and
  3. If there was a written agreement then it was not a "construction contract".

Two main issues arose at trial. First, under the main contract, did the Adjudicator have jurisdiction in respect of disputes arising "under the contract", or did his jurisdiction extend to disputes "under, out of or in connection with the contract". Second, were the disputes referred to the Adjudicator arising "under" and/or "out of or in connection with" the contract?

The contract had been amended. Article 5 provided that "if any dispute or difference arises under this Contract" then either party could refer that matter to adjudication in accordance with clause 39A. Amended clause 39A.1 provided that either party may refer any dispute or difference "arising under out of or in connection with this Contract to adjudication". [emphasis added]. The scope of Clause 39A.1 was therefore potentially wider than Article 5.

The defendant argued that Article 5 prevailed but Mr Justice Ramsey held that the contract needed to be read as a whole and that particular emphasis should be given to the bespoke amendments to the standard form that had been agreed between the parties. The Adjudicator therefore had jurisdiction to consider disputes arising under, out of or in connection with the main contract.

In October 2004 the parties had reached two agreements. The second October agreement was alleged to have waived liquidated damages and introduced a bonus scheme. Crosby argued that the disputes arose under the alleged side agreement, which was not in writing or was not a construction contract.

The Mr Justice Ramsay considered that the key issue was whether the side agreement was a separate settlement agreement or was a variation to the original contract. He held that unlike Shepherd Construction v Mecright the second October agreement in this case was not a full and final settlement agreement.

The true effect of the side agreement was to introduce a bonus system and relief to liquidated damages, which was a variation to the contract. While the parties, in the side agreement, did not specifically refer to the terms of the contract, it was clear that the effect of the side agreement was to amend provisions of the contract. As the side agreement amended the contract, and the contract contained a wide dispute resolution clause, then an officious bystander would conclude that the dispute resolution procedure under the contract applied to the side agreement. At paragraph 52 he stated:

"In this case, I consider that the side agreements fell into this category of agreements. It was necessary to have regard to the underlying Contract, in particular to see what liquidated damages had been waived. As a result, because, in my judgment, the side agreements were variations to the contract, I consider that the disputes under those side agreements would be properly categorised as disputes under the contract."

He went onto hold that the phrase "out of or in connection with" was wider than "under" the contract, and so even if the side agreements were separate obligations, then they arose out of or in connection with the contract such that the Adjudicator had jurisdiction in any event. Brown was therefore entitled to summary judgment.