Technology and Construction Court and the Civil Procedure Rules practice todayby Simon J A Tolson
Ambit of this paper:
|
||
1. TCC Construction and Engineering Protocol: is it working for the parties or lawyers? |
||
Going into a dispute with all guns blazing may
make you feel better, cause much blood on the carpet etc, but it's a
lousy way of keeping business and may well cost you an arm and a leg! So not only do you not have the right to declare war on the oppo when
you want before her majesty’s judges, in addition the rule book carries
a serious health warning if you start the off a bit too sharp! |
1. Woolf Report, Chapter 10, Paragraph 2 |
|
TCC Protocol (The Construction & Engineering Protocol)One of the major planks of the Woolf Reforms is that litigation is to be used as a last resort. The Civil Procedure Rules (CPR) introduced the novel concept of pre-action
protocols “to build on and increase the benefits of early but well informed
settlement which genuinely satisfied both parties to the dispute”. The
CPR specifically states that one of the aims of pre-action protocols
is “to put the parties in a position where they may be able to settle
cases fairly and early without litigation”. |
||
The Pre-action Protocol for Construction and Engineering Disputes (“the Protocol”) was implemented on 2 October 2000 for Construction and Engineering Disputes in the TCC. With a few limited exceptions(2) (including the making of an application for the enforcement of an adjudicator's decision) the Protocol should be used for all claims that are likely to be brought before the TCC. The aim of the Protocol is to promote an early exchange of information
and encourage the parties to reach a settlement or at least to agree
the most efficient way to manage any proceedings that may be necessary.
The general objectives The general objectives and aims of the protocol for construction and engineering disputes is the same as that for the other protocols in force. In essence it is to ensure that before the parties actually commence Court proceedings: -
The Protocol facilitates a clearer plan of how a case should progress pre-action. The protocol advocates a “cards on the table” approach and the spirit, if not the letter, should be followed in all sizes of claim. This is of course subject to proportionality of work and costs in small claims track cases. It assists and aids early exchange of information, better prepares the parties for litigation and ideally, persuades parties to formulate their cases earlier and so be aware of whether they should be seeking an alternative method of resolving the dispute, or even settling the matter, rather than charging into litigation. Of course, the work, time and cost in preparing an action prior to commencing litigation may still be substantial. Key features Key features of the Protocol include the sending of a formal claim letter and, once a response has been received, the holding of at least one Pre-Action Meeting. One of the items to be discussed at this meeting is whether the dispute could be more appropriately settled by way of some form of alternative dispute resolution. The Letter of Claim Most of us will be familiar with the traditional letter before action. The Protocol however requires something that is more substantive. As a first pre-action step, the Protocol requires that the Claimant or his Solicitor prior to actually commencing Court proceedings “shall” send to each and every Defendant a letter of claim. The Protocol states “if appropriate to his registered address”. It would be good practice to send a copy both to the registered and trading address. The Protocol requires the letter of claim to contain the following information:
Although not specifically stipulated in the Protocol, it is often prudent to append supporting documentation with the letter of claim by way of pre-action disclosure. It is not uncommon for a Claimant to write to a Defendant stating that damages yet to be quantified will be claimed or that an extension of time is to be sought but the period has not as yet been assessed. This of course, will no longer be acceptable without some attempt at either explaining why such a truncated approach is taken or some other intelligent sampling analysis. Parties must otherwise endeavour to set out fully their respective stalls from the outset. The Defendant’s response Once the Claimant has sent to the Defendant the letter of claim, the Defendant is required to acknowledge receipt in writing within 14 days. In the event that the Defendant fails to do so then the Claimant can commence proceedings. In my experience these times are adequate only in the smallest of claims and my opponents commonly these periods are extended by agreement sometimes to as much as 10 weeks or so. Upon receipt of the letter of claim, if the Defendant has any objections as to the Court’s jurisdiction, e.g. due to argument as to invocation of an arbitration agreement, or that the Claimant has the wrong Defendant, such objections should be raised within 28 days - subject again to agreed extension. In such circumstances, the Protocol does not require the Defendant to send a response to the letter of claim. If the Defendant fails to make such objections at this stage, he may nevertheless do so in subsequent Court proceedings. However, on the issue of costs, the Court may take this failing into account. The Defendant has 28 days from receipt to respond to the letter of
claim. The parties can however agree to extend this period up to a maximum
period of 4 months. If the Defendant fails to respond within 28 days
or, such period agreed between the parties, then the Claimant is ‘entitled’
to commence proceedings. |
2. Proceedings which include a claim for interim injunctive relief; where there is to be a claim for summary judgment pursuant to Part 24 of the CPR; where proceedings relate to the same or substantially the same issues that have been the subject of adjudication or some other formal ADR procedure
|
|
Where the Defendant’s response makes it clear that he has a counterclaim, then the Claimant must also respond within 28 days (or such period as the parties have agreed, up to a maximum of 4 months). The Protocol stipulates that the Defendant’s response contains information as to:
Pre-action meeting There is a requirement that the parties should meet at least once as soon as possible after the Defendant’s response, or where there is a counterclaim, to the Claimant’s response to the counterclaim. There can be more than one such meeting. The aim of which is to:
|
||
There is no prescribed format for the pre-action
meeting(s). However, the Protocol does envisage that a meeting will be
attended by suitable representatives who have authority to settle or recommend
settlement (3) and in addition where solicitors have been instructed,
one legal representative of each party. Furthermore, a representative
of the insurer should attend where their involvement has been made known
to the other party. |
3. Which occasionally can be a problem |
|
A question for the form Lord Woolf envisaged that the parties should treat the Courts as a last resort and other avenues to reach a fair settlement should be explored by the parties. This is reflected in the Court Allocation Questionnaires, which ask the question as to whether the parties wish to stay Court proceedings to attempt settlement. At the pre-action meeting, the parties are required to consider whether ADR may be appropriate. If it is evident that the parties are unable to resolve the dispute without recourse to the Courts, then they must use their best endeavours to try and agree such issues as whether a joint expert can be appointed, the extent of disclosure of documents and the conduct of the litigation with the aim of minimising cost and delay. Although the pre-action meetings are treated as being without prejudice,
the Court can and sometimes does require parties to disclose whether
a meeting took place, the parties in attendance, the identity of any
parties who refused to take part and an explanation as to why such a
meeting did not take place and any agreements reached. A party who therefore
refuses to participate runs a real risk of cost sanctions being imposed. |
||
Since the introduction in April 1999(4)
of the CPR parties are required to undertake considerably more of the
investigative work prior to commencement of any Court proceedings. The
introduction of the Protocol in this area of law undoubtedly provides
clarification and guidance to both practitioners and the parties to a
dispute as to what pre-action steps must be complied with. The objective
is for the parties to be made aware of the strengths and weaknesses of
their respective cases at an early stage and to seek a fair resolution
whether at the pre-action meeting or by some form of ADR. The Protocol
is intended to facilitate this. |
4. The CPR applies to proceedings issued after 26 April 1999, and also in large measure to proceedings current at that date. |
|
Beware failure to comply with the Protocol will likely result in cost sanctions against a defaulting party where Court proceedings are commenced without compliance to it. Its true adhering to the protocol has, in my experience, settled cases that would otherwise now be in Court, without the need for parties to incur substantial costs. In other cases where this has not happened, at least the issues in dispute have been narrowed. The protocol generally works well in practice and many clients like the fact that the first thing their lawyer says is “we should try and resolve this” rather than “let's issue a claim form”. Complying with the pre-action protocol itself has become a costly and
time-consuming process. It usually starts with a claimant producing
a detailed claim, often with expert evidence and witness statements,
and sometimes against a number of potential defendants. The strategy
is usually to force the parties to mediate and settle as quickly as
possible. Nothing wrong with that, many would say, and there is no doubt
that it often works. However, what if the case has no merit? The defendant
and its insurers are faced with a dilemma – they must convince the Claimant
that its case is futile, however, this will involve engaging an expert,
perhaps a lawyer, too, and incurring costs that it will never recover,
even if it persuades the Claimant not to pursue the case. If it ignores
the case, it risks the wrath of the Court if the matter ever comes before
a judge. Even if it wins, it may be penalised in costs for failing to
comply with the protocol. To put this in perspective, a defendant may
easily have to find a £50 -£100k sum to comply with the protocol in
a complex case. Remember, complying with the protocol is not compulsory.
In circumstances where you have a strong defence, then consider testing
the mettle of the Claimant – call its bluff and force it to start proceedings. |
||
The Law Society survey The Law Society has established the Woolf Network which each year compiles a Questionnaire on the Woolf Reforms, the 5th questionnaire dated March 2003 claims that 92% of the questionnaire respondents thought the CPR rules “were working well”, however a main concern was the insufficient enforcement of protocols. The TCC has developed judicial guidance through case law aimed at supporting
the protocols and the Judges have made it clear that the protocols should
be observed (see Paul Thomas Construction v Hyland & Anr(5)
and Liverpool City Council v Rosemary Chevasse Ltd). The Woolf
questionnaire, however, stated that 42% believed that the practice direction
on protocols was insufficient to enforce proper behaviour between the
parties pre-action. In 2001, the questionnaire stated that in only 31%
of cases were sanctions imposed for breaches of the protocols. The same
questionnaire also stated that 15% claimed the protocols had not generally
been complied with. This year’s questionnaire cited an inconsistent
approach by the Courts in the sanctions for breaches of the protocols
as a problem. |
5. 8 March 2000, (2001) CILL 1748 where, after the Claimant unsuccessfully applied for summary judgment he ordered that the Claimant pay the Defendant's costs to date on an indemnity basis because of the unreasonable manner in which the Claimant had conducted itself. |
|
The main effect of the protocols has been the development of front-loaded litigation. For lawyers the problem exists of how to reassure the parties involved that the extra effort and cost can, and does, yield the desired result without necessarily ending in a glory day in Court. Statistics recently published by the TCC(6) show that since the introduction of the Civil Procedure Rules in 1999 the number of writs/claims issued in the TCC has fallen drastically from 1,387 in that year, to only 386 in 2002, of which only 48 went to trial, the remainder either settling (321) or being transferred (5). Of course, when considering construction legal disputes due recognition must be given to the role of adjudication and its growth in usage as an alternative method of dispute resolution, which must have lead to a reduction in the number of claims in the TCC. However, there is a school of thought that adjudication has had next to no role to play in the reduction of TCC construction claims(7) . The TCC’s recent statistics also show that since the all time low figure of only 346 actions in 1999 the number of claims issued since has risen year on year, albeit slowly(8). Although these statistics indicate how construction disputes are being
disposed of, they do not tell us whether the parties and/or lawyers
are happier with the results produced owing to the involvement of the
pre-action protocol in disposing of the claims. There will be those
who used the protocol to conduct their litigation and feel it aided
a successful or fair judgment and those who didn’t make it to Court
either because the early collation of the claim and issues, as required
by the protocol, precipitated a settlement or an alternative dispute
method such as mediation was used successfully. |
6. Selected Statistics of TCC Business, 15 January 2003. 7. The Dispute Machine" Building Magazine James Bessey 29 June 2001 - claims that the reduction in TCC caseload came about post-CPR but prior to any real activity with adjudication and the Construction Act, namely 1999. 8. 1999 - 346 claims issued, 2000 – 344 claims, 2001 – 354 claims and 2002 – 386 |
|
Prior to the introduction of pre-action protocols it was suggested that lawyers needed to buck up their ideas and tackle claims referred to them from clients quicker and more thoroughly. It was thought the lackadaisical manner in which lawyers reviewed files. Particularly then non ORSA/TCC lawyers meant that a claim that was in fact not very strong or was even bound to failure was not being assessed as such until much later into the litigation process, usually involving the wasted time of the Court. A possible advantage of the protocol and its affect on the parties
and lawyers maybe not so much that it has made the whole dispute process
cheaper but at least with the options of settling or mediating a claim,
or being well-prepared as a client heads down the litigious route, the
desired result or a more satisfactory result is achieved for the parties,
who may feel that at least their money was well-spent. |
||
2. Adjudication enforcement and TCC practiceAdjudication offers rapid, cheap claims resolution, but has been hamstrung by doubts about how the Courts would deal with it. We have had approximately 130 published judgments about adjudication since it all started nearly five years ago and 6000 adjudications. Of these 130, five are from the Court of Appeal. Adjudications are supposed to be binding until the arbitrator or Court finally sort out the parties' disputes. But since the HGCRA came into force, many inroads have been made into the Adjudicator's power. For instance, the Courts have successfully disputed the binding nature of adjudications when adjudicators have decided points not referred to them, failed to decide points referred to them or behaved in a biased, unfair way. The effect has been to undermine the efficacy of adjudication. Yet since the introduction of the HGCR Act in 1996, adjudication has
steadily grown as a preferred method of resolving disputes. The first
case on the enforcement of an adjudicator's decision decided by the
Judge in charge of the Technology and Construction Court, took place
in February 1999, but it has been a well-worn path since then. The TCC’s
involvement in these disputes has been consistently part of their staple
diet since then. |
||
HH J Lloyd QC, the Judge in Balfour Beatty Construction v Lambeth(9) made an interesting aside, with which I concur, about the success of adjudication. He said:
|
9. [2002] EWHC 597 (TCC)
|
|
He then talked about the confidence that adjudication
has apparently earned. Put another way, after five years in the saddle
adjudication has been embraced a lot more seriously by industry than was
probably intended by parliament. Adjudicators have not regarded the machinery
as a knock-about process giving a rough and ready temporary answer. Instead,
they have worked their butts off to get an answer in the 28 days or thereabouts.
Whether the answer was right or wrong, is not the point I want to make.
The point is that the Adjudicators have used their technical know-how
and industry knowledge, got their gum boots on and their hands dirty to
try to reach a decision. So, they have earned a modicum of Court respect. |
||
But lets look at some of the enforcement cases thrown
out to illustrate the overall trend of the TCC, which is still to uphold
the adjudication process. |
||
In RJT Consulting Engineers v DM Engineering(10) the Court held that there was no “contract evidenced in writing”, and, therefore, that the Adjudicator had no jurisdiction. Its a moral for any client to get that document signed! Section 107(1) of the Construction Act provides that adjudication provisions
apply only where the contract is in writing. An agreement may be in
writing if “the agreement is evidenced in writing”. If a contract is
not “in writing” then the act does not apply and an adjudicator has
no jurisdiction. |
10. CA: Auld, Ward and Robert Walker LJJ: 8 March 2002 (LTL 8/3/2002), |
|
RJT Consulting was the third decision of
the Court of Appeal in respect of adjudication. It is an appeal from the
TCC decision of HHJ Mackay, who dismissed RJT’s claim for a declaration
that the construction contract was not an “agreement in writing” within
Section 107 of the Act. The Adjudicator had decided that the oral contract
was sufficiently evidenced in writing by drawings, schedules and minutes
of the meeting etc. HHJ Mackay agreed. |
||
However, the Court of Appeal allowed the appeal.
Lord Justice Ward and Lord Justice Robert Walker held that all of the
terms of the construction contract had to be evidenced in writing: “what
has to be evidenced in writing is, literally, the agreement, which means
all of it, not part of it” (11). It was not sufficient for
merely the material terms, such as the identity of the parties, nature
of the work and price, to be recorded in writing. Further, even if they
were wrong, the documents relied upon in this particular case were described
as “wholly insufficient”. Auld J considered that only the material terms
of the agreement were required, and therefore trivial or unrelated issues
did not need to be recorded. But the majority did not share his approach.
So on one view, all of the terms of the contract need to be recorded in
writing in order that a dispute under any contract can be referred to
adjudication. |
11. Lord Justice Ward |
|
Some might consider this an unfortunate decision, perhaps opening the door to a flood of jurisdictional challenges. The industry rarely records all of the material terms in writing, indeed those terms, which are material, are often not recorded in writing. However, the House of Lords has refused a petition to appeal. The Court of Appeal decided that it is not enough to have evidence in writing that supports the existence of an agreement. What has to be proved in writing is the whole of the agreement, not part of it. However, this could easily create serious problems for the industry, as contracts usually consist of express terms and implied terms. Put simply, the law will impute a term into a contract to give it business efficacy – to give effect to what businessmen must have intended. By way of an example, let us say a client wanted a local builder to stucco his property with a rare local lime based plaster. Several firms could supply the lime based plaster but it was not immediately available. Nevertheless, the builder promised to do the job and the client promised the builder that he would pay him fairly and properly. It was implied that the price would be a reasonable one, taking into account the current market value of the lime based plaster (rates for labour and other materials having been agreed). The duration of the contract was dependent on the procurement of the lime-based plaster and it was implied that the work would be carried out reasonably expeditiously. The parties intended to contract with each other, and a contract was concluded, even though most of the terms plugging the gaps were merely implied. This is a typically sieve-like construction contract – only watertight when all terms are taken into account. What the RJT ruling concludes is that, for adjudication to take place,
all the “express” terms of the contract must be evidenced in writing.
The Court of Appeal talks about a record “of everything which has been
said”. Parties to construction contracts are not always the most articulate people and the contracts they deal with are complex. Just as in my stucco example, it is frequently the case that not all contractual terms are evidenced in writing, nor even agreed verbally. Yes, there will often be a good answer when an adjudicator's jurisdiction
is challenged on the basis that the contract is not fully evidenced
in writing; however, if applied rigidly, the Court of Appeal's ruling
will mean that many disputes cannot be adjudicated at all, because they
are under contracts only partly recorded. |
||
Similarly in Debeck Ductwork Installation Ltd
v T&E Engineering Ltd .(12) |
12. 14 October 2002, TCC |
|
Here Her Honour Judge Kirkham followed the Court
of Appeal decision in RJT Consulting Engineers Ltd v DM Engineering
(Northern Ireland) Ltd (13)finding that where there is
an oral agreement between the parties, it is necessary for the purposes
of Section 107 of the HGCRA for all the terms of the agreement material
to the issue or issues in dispute to be clearly recorded in writing. Her
Honour Judge Kirkham suggested that in circumstances such as this, a party
should seek to clarify by way of a letter the terms, which he believes,
have been orally agreed and invite the other party to agree that those
are indeed the terms of the agreement. In this way a party would then
have the benefit of the protection of Section 107 of the HGCRA. |
13. (CILL 2002, 1841) |
|
In this case Debeck was engaged by T&E
for the installation of air-conditioning services as part of a pharmaceutical
development in Basingstoke. The parties reached an oral agreement whereby
Debeck agreed to undertake the installation of ductwork for £27,000
plus VAT. The work was carried out by Debeck but no payment was
made by T&E. Accordingly, Debeck made an application
for summary judgment arguing among other things that the contract was
a construction contract within the meaning of the Housing Grants Construction
and Regeneration Act 1996 and that accordingly, in the absence of any
Section 110 or Section 111 notices, summary judgment should be granted.
|
||
T&E denied that the Housing Grants Construction and Regeneration Act 1996 was applicable, maintaining that there was no agreement in writing. Debeck relied upon Section 107(2)(c) and 107(4) of the Act, maintaining that, for the purposes of the Act, there was an agreement in writing as that agreement was evidenced in writing within the meaning of Section 107(2)(c) of the Act. Debeck relied on a fax sent to T&E on 25 March
2001, which Debeck submitted contained all the relevant terms of the
agreement and was thus sufficient to constitute written evidence of
the agreement. Her Honour Judge Kirkham rejected this submission on
two counts. First, the fax did not set out or record all of those matters
on which Debeck itself relied on in pursuing its claim. For example,
the fax did not explain even in summary terms the scope of the work
to be undertaken; it was not clear whether materials were to be supplied
or not; and the sequencing and programming of the work was also unclear.
Second, a director of T&E gave evidence that there were
further terms of the contract between the parties upon which T&E
relied which were not recorded in the fax. For example, these matters
included references to the specification or standard to which work was
to be carried out, matters as to quality and issues as to the timing
during which work was to be undertaken. Her Honour Judge Kirkham concluded
that it would be quite wrong that a party should be entitled to rely
upon a document which it was said contained all of the relevant terms
in circumstances where there were additional material terms which the
other party says were agreed orally. |
||
Then lets look at Carillion Construction v Devonport Royal Dockyard(14) , it represents one of the most recent inroads. Carillion was retained by Devonport to carry out work. After the project ran into problems, the parties discussed changing the basis of payment. It was said that agreement had been reached, orally, between them on 30 October 2001. There was no written agreement to this effect. Later, in August 2002, Carillion began an adjudication based on its entitlement under the alleged oral agreement. The Adjudicator decided that Carillion should be paid £7.5m Devonport was not prepared to pay because it argued the Adjudicator had no jurisdiction to adjudicate on what was an alleged oral variation to the contract. The matter came before His Honour Judge Bowsher in the Technology and Construction Court on 27 November 2002. He found in favour of Devonport. In doing so, the Judge relied on the earlier Court of Appeal case of RJT Consulting v DM Engineering, which determined that there must be a construction contract made, or evidenced in writing, if an adjudicator was to have jurisdiction. Moreover, said RJT, the contract was not evidenced in writing merely because there were documents that indicated its existence; all the terms of an oral agreement must also be in writing. The Judge found that the alleged agreement was not evidenced in writing and, accordingly, that the Adjudicator had no jurisdiction in these circumstances. There has been no appeal. |
14. 27 November 2002 |
|
The effects of RJT, Debeck and Carillion may prove serious for adjudication in the UK. As the Judge accepted, disputes over oral construction agreements are very common. It is often the case that important terms of a contract are orally agreed. Parties, often at a site level, agree to vary terms of the contract, sometimes consciously, sometimes not. Such terms are often not incorporated into the signed contract or a formal variation of terms. Accordingly, unless oral terms are put in writing, their existence will secure the non-applicability of adjudication. The RJT case determined that all terms must be evidenced in writing; the Carillion case determines that this applies to oral variations of written terms. If any contract term or any contract variation is not in writing, there is no right to statutory adjudication. Even if the orally agreed terms are unimportant, this will apply. It is likely therefore that many such construction contracts even if mostly evidenced in writing will fall outside the act. Respondents to adjudications will be able to run the argument before adjudicators that there were oral terms agreed between the parties and that accordingly the Adjudicator does not have jurisdiction. Even if the Adjudicator rejects that argument, the losing party can
apply to the Court for declarations that the Adjudicator had no jurisdiction;
provided that there is an arguable case that any terms were not evidenced
in writing, they will at least delay the enforcement of any adjudication
decision; at worst, the decision will be found to be unenforceable. |
||
These decisions in Carillion and RJT,
will undermine the efficacy of adjudication. When consideration is given
to amending the statutory provisions, attempts must be made to put right
this serious problem. |
||
For the benefit of those that do not know, either
party can apply to the TCC to have an adjudication decision summarily
considered and obtain a formal and enforceable judgment. An adjudication
decision is not open to appeal in the way a normal Court judgment is.
If a party commences proceedings around the decision obtained it is either
to enforce it and require the losing party to comply with the decision
(using breach of contract as a basis of claim) or the entire dispute can
be re-tried in the Court. The TCC will not, however, interfere with an
adjudicator’s decision just because it appears wrong .(15) |
15. See “Keep it Clean” Building Magazine, Tony Bingham 6 December 2002 |
|
Outwith jurisdiction issues, and fundamental and paramount errors that go to the root of a contract, of which more below, the TCC will only overturn an adjudicator’s decision on the basis of a procedural irregularity, i.e. lack of jurisdiction by the Adjudicator, lack of impartiality or apparent/existent lack of natural justice during the process i.e. unfairness .(16) Although the TCC’s role in adjudication would appear fairly restrictive
it has the power to review its own relevance in this area. As seen above
the TCC has decided for itself the grounds on which an adjudication
decision can or cannot be challenged and signs exist that the TCC is
developing importance and prevalence in this legal area. If the receiving
party is in liquidation or receivership or there is a serious doubt
about its ability to repay then a stay of execution may be granted.
This principle was recognised in Bouygues v Dahl-Jenson, but
has more recent application in the case of Rainsford House Limited
(in Administrative Receivership) v Cadogan Limited(17)
. In that case, Rainsford fell into the category of “serious doubt on
the ability to repay” by the very fact that they were in administrative
receivership. The recent case Baldwins Industrial Services v Barr
Limited(18) involved Birmingham TCC ordering a payment
into Court of the money, which had been adjudged due by an adjudicator
and ordered to be paid to the winning party. Baldwins is an
example of the situation where the Adjudicator’s decision is up for
re-trial and the losing party is worried if the money is paid over meantime
it may end up being lost in a financially weak company, and in the event
that the litigation is won the money will not be recoverable. In ordering
such payments into Court, however, the TCC is going against the concept
of adjudication, which was designed to improve cash flow in the construction
industry despite the inevitable disputes that crop up .(19) |
16. See Discain Project Services Ltd v Opecprime Developments Ltd (2001) which established that the rules of natural justice are applicable to the adjudication process. 17. 13 February 2001 18. TCC, 6 December 2002 19. See “Freezing Points” Building Magazine, Tony Bingham 24 January 2003. |
|
Bovis Lend Lease Limited v Triangle Development Limited (20) What of the status of an adjudicator’s decision? Can you withhold against it? This is a topical issue on enforcement. In Bovis Lend Lease Limited v Triangle Development Limited, Bovis was a management contractor for Triangle Developments for the fit-out of three Victorian schools into three residential apartments. The contract was in the form of the JCT Standard Form of Management Contract 1998 Edition. The contract contained, at clause 7.6.4.1, a clause which stated that any further payment or release of retention shall not apply as a result of the determination of those in his employment. A dispute arose in respect of the valuation of two interim certificates, in which the architect had reduced certain sums so that each of the two certificates certified a negative value to Bovis. The architect also served a notice on Bovis to the effect that they were failing to proceed regularly and diligently with the works. Triangle then issued a withholding notice in respect of liquidated and ascertained damages following a certificate of non-completion. Bovis claimed that Triangle had repudiated the contract by engaging new contractors, and that Bovis had accepted that repudiation. During this period three adjudications were being progressed. The first related to the negative interim certificates, the second in respect of Triangle’s claim that Bovis was in breach for a requirement to provide documents and the third relating to the question as to whether the contract had been repudiated. A variety of questions arose, but one central question related to the status of an adjudicator’s decision. The first Adjudicator’s decision was in conflict with the third in respect of the payments of sums due. The first decision related to the interim valuation, whilst the third related to payments of sum due as a result of the counting process upon determination of the contract. HHJ Thornton QC held:
Judge Thornton’s decision in Bovis v Triangle opened the door
in one fell swoop for contract drafters to devise terms, which would
rob adjudicator’s decisions of their teeth. The Court of Appeal has
revisited the early authorities such as Macob v Morrison and reaffirmed
the purpose of adjudication - to produce a binding and enforceable interim
award. In light of this Levolux is a plea for sanity answered. |
20. 2 November 2002, TCC, HHJ Thornton QC |
|
Levolux AT Limited v Ferson Contractors Limited (21) | 21. 26 June 2002, TCC, HHJ Wilcox |
|
The question in this appeal is whether the Adjudicator’s
decision should be enforced in the derogation of contractual rights, which
could be in conflict with the decision. The dilemma in Ferson
has cropped up several times before: what is to be done when an adjudicator's
decision requires A to pay B but the contract between A and B is in conflict
with that decision? Trouble arose around the second interim payment. In
the High Court, before the first instance Judge, Counsel for Ferson
relied on two previous first instance judgments. The first, K&S
Industrial Services (Birmingham) v Sindall(22) , decided
that if the contract has been lawfully terminated by the time an adjudicator
requires payment, then that payment does not have to be made. The second,
Bovis Lend Lease v Triangle Developments, which as we have seen
explained that if a term existed in the contract that had the effect of
superseding or avoiding or allowing deductions from the payment directed
by an adjudicator's decision, then those terms prevailed over the Adjudicator's
decision. |
22. 2000 TCC 17.7.00 CILL 1652 |
|
I and other construction lawyers last Christmas said the Triangle Developments and Parsons Plastics v Pirac(23) decision before it would persuade paying parties to write that type of deduction clause into their contracts and cause untold damage to adjudication. So Levolux came not a moment too soon. The Claimant, Levolux, was a sub contractor engaged under the GC/Works sub contract with amendments to supply and fit brise soleil and louver panels for the Defendant, Ferson, Levolux served a notice of intention to refer a dispute to adjudication dated 25 March 2002 in respect of a failure to pay application number 2. The Respondent relied upon a notice of withholding payment, but Levolux contended that the notice was not a valid notice within Section 111 of the Act. The Adjudicator issued his decision dated 30 April 2002 which held that the withholding notice did not comply with the requirements for Section 111 of the Act and therefore concluded that payment of £51,659 inclusive of VAT, together with interest, costs and the Adjudicator’s fee should be paid by to Levolux. The Claimant claimed summary judgment for the amount of the decision. However, the Claimant had commenced the action pursuant to CPR Part 8 (alternative procedure for claims) rather than CPR Part 24 (the part dealing summary judgment). The Defendant accepted that the matter could be heard as a Part 24 matter. The Defendant’s primary case was that it had determined the sub contract.
Alternatively, the Defendant argued that it could rely upon the amended
clause and set off and/or counterclaim against the decision of the Adjudicator.
The amendment to the GC/Works sub contract stated at clause 38A.11 “neither
party shall be precluded from raising any right of set off, counterclaim
or abatement in connection with the enforcement of an Adjudicator’s
decision”. The Claimant had suspended the works as a result of non-payment.
The Defendant then issued determination notices for failing to proceed
regularly and diligently. The dispute referred to adjudication was in
respect of the valuation and withholding, and did not include an issue
in respect of determination. |
23. Neither Parsons nor Bovis involved a “construction contract”. Neither was subject to the Construction Act. Both had elected to use adjudication voluntarily. Adjudication and the payment provisions are only compulsory when your contract is a construction contract as defined in the Construction Act. If your project is a construction project, you cannot include in your contract a clause that defeats the intentions of the act. Such a clause will be struck down. An adjudicator can decide so; or the Court can at enforcement stage. The clause that is contrary to the Construction Act will be shown the red card. |
|
HHJ Wilcox held that the amount owing pursuant to the Decision should be paid to the Claimant. This was on the basis that the parties had accepted, by reference to clause 38A7 of the contract that a decision would be binding pending litigation or arbitration. The amended clause 38A.11 in respect of a right to withhold and/or set off against an Adjudicator’s decision was in conflict with Section 111(1) of the Act requiring an effective notice. Therefore, HHJ Wilcox enforced the Adjudicator’s decision. The Defendant raised several issues by way of appeal. First, they argued that the contract had been validly terminated, and so the Adjudicator’s decision was inconsistent with the determination. Lord Justice Mantell held that that argument was rejected, as the first instance Judge had held that there had plainly been no valid determination. It was the Adjudicator’s decision that payment should be made, on the basis that the Withholding Notice was invalid, that meant that the subcontractor had a right to suspend such that the Contractor did not have a right to determine the contract for wrongful suspension. Second, the Defendant argued that there were some exceptions to the principle that an Adjudicator’s decision is binding and enforceable pending final resolution by arbitration or litigation. In respect of this appeal, one of those exceptions was that the terms of the contract to stated that no further payment would be made as a result the obligation to make a payment in accordance with the Adjudicator’s decision. This exception was based upon HHJ Thornton QC’s judgment in Bovis Lend Lease v Triangle Developments (2 November 2002). Lord Justice Mantell considered that case and the cases upon which Bovis relied. He came to the conclusion that the logic in the cases relied upon by HHJ Thornton was insufficient to support the conclusion reached in Bovis. However, Lord Justice Mantell construed the terms of the contract so as to give effect to the Adjudicator’s decision, and so held that the determination clauses must be read as not applying to amounts due by reason of the Adjudicator’s decision. He therefore dismissed the Appeal. Lord Justice Longmore, and Lord Justice Ward agreed. Thus the Court held that Ferson and Judge Thornton were wrong. The purpose of s108 was clear. It was a speedy mechanism to settle disputes and lead to enforceable immediate payment obligations. If Ferson and Judge Thornton’s arguments were correct then the purpose of adjudication would be defeated. Any clauses that are inconsistent with s108 must be read as not applying to monies due by reason of an adjudicator's award. What then of mistaken adjudicator – how far wrong of the tracks
must he be? |
||
The second Court of Appeal decision relating to adjudication, and touching on Section 111 withholding notices was C&B Scene Concept Design Limited v Isobars Limited, 31 January 2002. The case concerned the jurisdiction of the Adjudicator, and appeared to focus on appendix 2 of the JCT WCD. In the absence of the selection of either payment alternative A or B, the Judge decided that the payment mechanism fell away and was replaced with the Scheme. The result was that the decision was not enforced. At the summary judgment application in the TCC, three reasons for non-compliance with the Adjudicator’s decision had been advanced. First, since the parties had failed to select alternative A or B, the whole of clause 30 fell away, the provisions requiring the employer to give notice also fell away, and the provisions of the Scheme applied. Second, failure to give notice does not preclude the employer from arguing that sums are not “due under the contract”. Third, the Adjudicator had asked the wrong legal question by failing to appreciate that clause 30 had been superseded by the Scheme. Sir Murray Stuart Smith considered that the real question was whether the error on the part of the Adjudicator went to his jurisdiction. He applied the law which has developed in respect of expert determination, citing the test set out by Knox J in Nikko Hotels (UK) Limited v MEPC plc [1991] 2 EGLR 103:
Sir Murray Stuart Smith concluded that the Adjudicator was asked to decide the amount of the interim application number 6. Within the scope of that referral the Adjudicator may have made some errors of law along the way, he had not exceeded his jurisdiction. He has decided the matter put to him and the decision would be enforced. The Court of Appeal simply avoids the issue by referring to the law
on expert determination and making its decision on that basis. The question
of whether clause 30 of the contract, or the payment provision of the
Scheme, were to apply (and so a consideration of whether a valid withholding
notice had been given) was not considered. Instead, the Adjudicator
had jurisdiction to consider which terms where to apply, and whether
right or wrong, his decision would be enforced.
|
||
The Courts have at first instance given some consideration to the applicability of the public law principals to adjudication. Lord Reed in the case of Ballast plc v The Burrell Company (Construction Management) Limited (21st June 2001) considered that Lord Reid’s principles were applicable to adjudication, and provided some useful guidance for determining when an adjudicator might be able to make a decision that was both wrong in law and in fact, but should nonetheless be upheld, and those situations where the line had been crossed such that the decision was in excess of jurisdiction and unenforceable. However, HHJ Seymour QC in the more recent case of Shimizu Europe Limited v Automajor Limited (17th January 2002) rejected the public law approach of Anisminic or the Wednesbury principles(24). This appears to be on the basis that the judicial review principles, whilst applicable in Scotts Law were not applicable in English law. Summing up On more settled ground is the approach to enforcement of the Court, by way of analogy to the test in expert determination. Provided that the Adjudicator has asked the right question, then the Adjudicator has the jurisdiction to reach an enforceable decision even where that decision is wrong in fact or law. While this approach allows the Court to simply assess the jurisdiction of the dispute in question and come to a conclusion about its enforceability, it does not provide an opportunity for the Courts to address some of the wider issues. The Courts have in some instances adopted a more cautious approach
to the enforcement of adjudication. However, it must be right that both
parties understand the subject matter of the dispute that is to be referred
to adjudication, and can expect the “natural justice” safeguards to
apply to the process of adjudication as one would expect those proper
checks and balances to apply to any dispute resolution process. Nonetheless,
the case of RJT Consulting may provide many opportunities for
jurisdictional challenges on essentially technical grounds. Levolux
means that one must cross adjudicate in order to defeat a decision relating
to interim contractual processes, such as interim valuations. It remains
to be seen whether future Court of Appeal cases will adopt such a restrictive
approach or whether we will see a return to the purposive approach originally
pioneered by His Hon Mr Justice Dyson. |
24. Wednesbury unreasonableness relates to “a decision, which is so outrageous in its defiance of logic or accepted moral standards that no sensible person who had applied his mind to the question to be decided could have arrived at it.” Per Lord Diplock in Council of Civil Service Union v Minister for the Civil Service [1985] AC 734 House of Lords referring to Associated Provincial Picture House Limited v Wednesbury Corporation [1948] 1 KB 223. 25. David McLean Housing Contractors Limited v Swansea Housing Association Limited (27th July 2001) |
|
3. Case Management and CMCs – better than the old days?Where it started As Lord Woolf said:
Lord Woolf made the template and set the scene with a number of major new principles to make the system of civil justice more efficient and productive. He said in Access to Justice:
|
||
In the TCC where a claim form is marked “Technology
and Construction Court” and issued in the Royal Courts of Justice, (26)
the case will be assigned to a named TCC Judge (the “assigned Judge”)
who will have the primary responsibility for the case management of that
case .(27) |
26. Issue is at St Dunstan’s House. 27. Para 2.4 of PD49C. |
|
As commentators have remarked many times, case management by the Court is central to the Civil Justice Reforms. The impact of case management in TCC cases is probably less than in any other area of litigation, for two reasons. First it is a major part of the case management approach that the Court will allocate each case to an appropriate track; all TCC cases, however, are treated as fast track cases. Secondly, Lord Woolf’s reforms were modelled upon the sort of case management techniques developed by the Official Referees(28) and in particular the technique whereby the Court, at an early stage, fixes a trial date, and sets a timetable for the whole matter leading to that date(29) . The case management provisions in the CPR have nevertheless had a material impact even in TCC cases. Court’s Duty To Manage Cases Rule 1.4
|
28. Woolf Report, Chapter 1, paragraph 2. 29. It is notable that, during this period, the Official Referees and then the Judges of the TCC have repeatedly attempted at an early stage to gain some understanding from the parties as to what the case is really all about. The practical constraints of time, however, has meant nevertheless that the Court has in large measure been dependant upon the parties’ own assessment of what is necessary in terms of evidence, what would be helpful by way of preliminary issues etc. |
|
Proportionality is a key concept, but there is no express guidance as to what is proportionate. It is obviously not proportionate for litigation to cost more than the amount in dispute, but that has traditionally been the norm in contested construction cases. The role of ADR in litigation is now enshrined in the CPR. By Rule
1.4 (1) the Court must further the overriding objective by actively
managing cases, and by Rule 1.4(2) active case management includes encouraging
the parties to use an alternative dispute resolution procedure if the
Court considers that appropriate and facilitating the use of such procedure. |
30. CRP 3.1(1) |
|
Procedures for case management The key to case management in the TCC starts with the application(31) for directions (including an application for a fixed date of hearing), which must be made by the Claimant within 14 days of the filing by the Defendant of an acknowledgement of service or of a defence (whichever is the earlier)(32) . If the Claimant does not make such application, then any other party may do so or may apply for the claim of the Claimant in default to be struck out or dismissed, or a TCC Judge may fix the hearing on his own initiative(33) . In my experience of TCC cases in London the Judge usually fixes a date of his own motion well before a defence is served. Para 5.1 of PD49C provides that the first case management conference will take place at this directions hearing, but not always, as if the Judge thinks more time for consideration is needed, he will adjourn the first hearing in order that the case management conference can be heard later. This is particularly likely in multi-party cases where one or more of the Defendant wants to bring Part 20 proceedings against additional parties. There is no prescribed form for the application.
|
31. Applications are used in building disputes in a multitude of different ways: -to ensure compliance with previous court orders; for extensions of time; seeking summary judgment, or interim payments; but the increasing role of case management now means that parties are expected, wherever possible, to make their applications at the case management stage. 32) Or, if the action is transferred to the TCC, within 14 days of the date of the order of transfer. 33) Para 4.3 of PD49C |
|
When the Court notifies the parties of the time and date of the hearing of the first case management conference it also sends them a case management questionnaire(34) and a case management directions form(35) . The parties have to complete, exchange and return both forms by no later than 4 pm two days before the date on which the case management conference is to take place. The parties are encouraged to try to agree directions by reference to the case management directions form. |
34.Form TCC/FCM1 35. Form TCC/CMCDDIR |
|
In complex cases, parties typically also put in skeleton arguments as to the directions they want and why; the form of these skeletons differs little from the old practice. If a party fails to exchange or return the forms by the date specified, the Court may make an order, which leads to the claim or defence being struck out, or impose such other sanction as it sees fit, or may hold a case management conference without the forms. At the first case management conference, the Court will usually fix the date for trial of the case and of any preliminary issue that it orders to be tried. It will also give case management directions e.g. pleadings, disclosure, experts, witness statements. The directions will usually include the fixing of a date for a pre-trial review. If the parties have agreed proposals for the management of the proceedings
(including a proposed trial date or period in which the trial is to
take place) and the Court considers that the proposals are suitable,
then it may approve them without a hearing and give directions in the
terms proposed(36) . |
36. CPR 29.4 |
|
Recent findings The Civil Justice Reform Evaluation - Emerging Findings(37)
was a report put together by the Lord Chancellor’s Department in March
2001 to assess the effects and outcome of the civil justice reforms
at a fairly early stage (only 11 months after implementation). The report
suggests that CMCs “appear to have been a success”, however, two years
on is this still the case? The CMCs are possibly slightly reflective
of the other European inquisitorial systems, though of course the powers
of the English Judge are no where near as extensive ie in France, where
the Judge or judge generally has primary responsibility for
defining issues in dispute and investigating evidence resulting in the
case in Court being judge led as opposed to party led. The latest report
from the LCD - Further Findings published in August last year (2002)
stated that one of the main effects of the CMCs is the reduction in
the number of applications being made during litigation and 98% pf questionnaire
respondents said the CMCs “were working very well or quite well”. |
37. Published by the LCD in March 2001 |
|
However, when considering CMCs and judicial intervention
in the running of litigation it should not be forgotten that the Judges
of the pre-TCC Judges were seen as leading interventionists. Andrew Burr’s
article “The Post-Woolf TCC: Any Change?”(38) discusses the
gusto with which the TCC Judges have grasped the idea of further judicial
intervention with the wider powers granted through the CPR and the concept
of Case Management. |
38. 17 Const LJ 5 pp.378-394 |
|
4. Speed and accessibilityOne thing is for sure, compared to the heady litigious days of the late 1980’s to mid 1990’s, the TCC issue room today is not what they used to be – volume is down and the price of issue of process in an anti Woolf way a high one! Recent figures published by the TCC in January show the following waiting times: Trials up to 4 days - January 2003 onwards Unfortunately, there are no comparable figures available from the TCC
for previous years. However, the Further Findings report states that
generally, post-CPR, the time between issue and hearing for cases that
proceed to trial has decreased(39) and 51% of the trials
took less than a year. Recently in major proceedings I had issued in
December 2002 a 32 case was listed in an open judicial diary, as a first
and only fixture for 32 days in January 2004. |
39. Interestingly, for small claims that waiting time has risen. |
|
5. Experts and TeCSA Expert Witness ProtocolIntroduction In his Final Report on Access to Justice (July 1996) Lord Woolf discussed at length what he perceived to be the principal problems with expert evidence in litigation. These were as follows:
Who is an expert witness?
Independent, objective, unbiased, honest CPR 35.3: The Expert's Overriding Duty is to the Court
Rule 35.3 of CPR Part 35 states as follows:
Lord Woolf’s Final Report contained 7 key recommendations as to how these perceived problems were to be remedied. These recommendations are as follows:
These key principles endorsed by the Court of Appeal in Ikarian Reefer, were widely circulated and became the standard by which experts were judged. Despite the general acceptance of these criteria, that acceptance did not take effect quickly enough to prevent growing judicial dissatisfaction with the way in which expert evidence was presented. Lord Woolf highlighted three “problems”: excessive cost, lack of impartiality and the emergence of an “expert industry”. A number of decisions followed which clearly took note of some of these principles. Whilst Mr Justice Dyson’s attack, in Pozzolanic Lytag Ltd v Bryan Hobson Associates (1998) CILL 1450, on the conduct of experts and their “prolix reports” was widely publicised, the Courts were also alive to the second of Lord Woolf’s concerns, namely lack of partiality. In London Underground Ltd v Kenchington Ford plc and Others (1998) CILL 1452, HHJ Wilcox criticised one expert for adopting a partisan approach, noting that he”… signally ignored his duty to both the Court and his fellow experts” and “continued to assume the role of advocate of his client's cause.” This undoubtedly affected the weight given to that evidence, characterised as being “invalid and unscientific”. In a second case, Munkenbeck and Marshall v Kensington Hotel (1999) 15 Const LJ 231, HHJ Wilcox went further and expressly downgraded the evidence of an expert who “… badly lost sight of the proper role of an expert assisting the Court in the determination of issues … adopted the stance of an advocate. The value of his evidence was thus very greatly diminished. I was wholly satisfied with the evidence of Mr Melvyn; an impressive witness and a fair and objective witness”. These criticisms were reinforced by the Court of Appeal in Clonard Developments Limited v Humberts (unreported Court of Appeal 15 January 1999), which upheld a trial judge’s decision to reject the evidence which was “unhampered by impartiality” of the expert witnesses of both parties. The Court of Appeal warned that:
Restrictions on the use of expert evidence The general principle for the last 4 years is that if expert evidence is required it will have to be justified (at an early stage in the proceedings) and, that in accordance with Rule 35.1 of CPR Part 35, the Court is under a duty to restrict expert evidence, “to that which is reasonably required to resolve the proceedings.” This places burden of justifying the need for expert evidence in the proceedings squarely upon the parties. It follows that if a party cannot convince the Court of the need for expert evidence such evidence will not be permitted and the party will have to proceed without it. Under the old regime the Court’s permission was always required to adduce expert evidence and this is reiterated in the new rules in CPR Part 35 Rule 35.4(1). The difference is that, under the CPR the granting of permission to adduce expert evidence will not be automatic. Note that the test in Rule 35.1 is not whether expert evidence is required but whether it is reasonably required. We can expect submissions in support of expert evidence to be closely scrutinised by the Courts that will apply the principles of the overriding objective set out in CPR Part 1. In my expectation the Courts will deal rather brusquely with applications to adduce expert evidence in ‘simple’ or smaller actions of less than £100,000 and where an obvious argument for independent opinion evidence cannot be made out. There are indeed one or two TCC Judges that make the admission of such evidence remarkably difficult. A fair number of applications to adduce expert evidence of various disciplines are likely to be rejected, no doubt to the surprise/consternation of the parties and their lawyers. In relation to certain types of litigation, for example, medical negligence and personal injury cases, the Courts have been more brusque still. (It is generally accepted that curbing the proliferation of expert evidence with these two areas is a specific object of Lord Woolf’s reforms.) Assuming a party obtains permission to adduce expert evidence the new
rules contain a further restriction upon how the evidence is to be presented.
Rule 35.3 establishes a presumption that expert evidence will be given
in a written report. Oral evidence from an expert supplemental to the
report is intended to be the exception rather than the rule. If a party
anticipates that oral evidence will be required, this requirement will
have to be justified to the Court, which will be likely to pose the
sometimes difficult question, “Why?” in response. The overriding objective
will again be applied. |
40. a) It is the duty of an expert to help the
Court on the matters within his expertise. This duty is paramount and
overrides any obligation to the person from whom the expert has received
instructions or by whom he is paid. |
|
It is important to note that under CPR Part 32 Rule 32.1 the Courts have a general power to control the evidence(41) to include the exclusion of otherwise admissible evidence and limit cross-examination(42) . In reality the Court always possessed the power to ignore inappropriate expert evidence (e.g. evidence that was irrelevant or reflected the expert’s attempt to act as an advocate)(43) but this power is exercised more forcefully and proactively in the spirit of the new rules. The rules also contain a sting in the tail that from the outset the Court is entitled to limit in advance the costs a party may ultimately recover in respect of the fees and expenses of an expert upon whose evidence they propose to rely(44). This power to “cap” experts’ costs may make the party think twice about using expert evidence at all. However I have not seen it exercised as yet. The TeCSA Expert witness protocol It started in 1996(45) with the Official Referee's Solicitors Association (ORSA) protocol 1.0 to promote the interests of solicitors and their clients conducting business in the Official Referee's Courts and in related arbitration. The then Committee of ORSA rightly believed that the relationship between
solicitor and expert witness is of the utmost importance in view of
the duties each owes to the Court or other tribunal. The first protocol
had been prepared with a view to assisting clarity of communication
and in order to provide a framework within which solicitors and experts
are able to operate freely. It was not intended that the protocol should
operate in a rigid way but that reference to it would enable experts
and solicitors to consider key areas at an early stage. |
41. Rule 32.1(2). 42. Rule 32.1(3). 43. See for example Alliance & Leicester Building Society and Others v Edgestop Ltd and Others [1997] 3 Con. L.Y.B 93 44. CPR Part 35 Rule 35.4(4). 45. Official Referee’s Solicitors Association Expert Witness Protocol 1996 CILL Page 1216 |
|
Its publication arose out of the ORSA Response to the Issue Paper on Expert Evidence released by the Access to Justice Team in January 1996. The new version 2.0 TeCSA Expert Witness Protocol has been produced as a revised guide to experts when providing expert evidence be that in the TCC or arbitration. The guide holds to its original aim of not intending to be restrictive or rigidly applied but is a means of regulating the relationship between solicitor and expert, whilst also aiming to help experts fulfil their role properly and adequately. The protocol is an additional tool to be used in conjunction with Part 35 CPR and one of its aims is to reinforce the independence and impartiality of the expert. The protocol does not repeat or restate the technical legal requirements of the CPR rules it is more concerned with defining the solicitor/expert relationship ie part B relates to the nature and contents of the brief to be given to the expert by the solicitor, parts D and E are concerned with Without Prejudice Expert meetings. Although observance of the protocol is not compulsory, its use in making
sure that Part 35 is properly observed and that an expert carries out
his role appropriately cannot be underestimated. The Courts have shown
and continue to show that if an expert is not seen as impartial, independent
or of any practical use in solving a dispute then that evidence can
be dismissed from the action(46) . |
|
|
With this in mind I leave you with the best practice expert declaration, it sums up the legal requirements in a nutshell:
|
46. Stevens v Gullis [1999] 10 Build LR 394 and in Anglo Group plc v Winther Browne & Co Ltd and another 72 Con LR 118, HHJ Toulmin stated after discussing, the requirements of an expert witness and expert evidence referring to the Ikarian Reefer : “124. I find that neither [of the Experts] conducted themselves as independent expert witnesses or in a manner acceptable to the Court. I am unable to rely on their evidence in support of [the 1st Defendants] as independent expert evidence.” |
|
For those of you who have not accessed the TeCSA website lately I set out the Protocol in full below. EXPERT WITNESS PROTOCOL – Version 2.0 The Technology and Construction Solicitors Association (TeCSA) was formed to promote the interests of solicitors and their clients conducting business in the Technology and Construction Court and in related arbitration. The Committee of TeCSA believes that the relationship between solicitor and expert witness is of the utmost importance in view of the duties each owes to the Court or other tribunal. This protocol has been prepared with a view to assisting clarity of communication and in order to provide a framework within which solicitors and experts are able to operate freely. It is not intended that this protocol should operate in a rigid way but it is hoped that reference to it will enable experts and solicitors to consider key areas at an early stage. The publication of this protocol arises out of the TeCSA Response to the Issue Paper on Expert Evidence released by the Access to Justice Team in January 1996. TeCSA hopes that this protocol will encourage independence and impartiality of the expert. Not all of this protocol will apply to every appointment and there will inevitably be areas, which the protocol does not specifically cover. It is intended to keep this protocol under review and comments will be most welcome. TeCSA supports the Code of Practice published by the Law Society and acknowledges comments made by many bodies and individuals as part of the consultation process. Protocol |
||
A. Section 1 The solicitor shall
provide sufficient information to the expert to enable the expert to
confirm whether or not the issues, as identified by the solicitor, are
matters on which the expert is competent to act as expert witness. The
expert should be satisfied that he has the necessary resources to meet
the requirements of the appointment, including the required timetable.
TeCSA encourages the appointment of experts who maintain active professional
practices. 2 The solicitor shall
provide the expert with a list of relevant parties and the expert shall
state whether or not he has any connection with any of the parties named
or to be reasonably inferred from the list to enable the solicitor and
the expert to consider whether any conflict of interest exists. 3 The expert should
normally expect to provide information about his expertise and experience
and suitability for the role for which he is being considered together
with details of his proposed basis of charge. If the solicitor intends
to approach more than one person to discuss his or her potential suitability
for appointment as an expert witness, he should inform each expert that
he is one of a number under consideration. 4. In any selection
and appointment process the solicitor should remember that a witness
who is not selected or whose appointment is subsequently terminated
may be free to accept an appointment from other parties. The solicitor
may wish to ensure that documentation and information made available
as part of any selection process is carefully chosen, commensurate with
the requirement to provide relevant information, and that documentation
is retrieved at the end of the process or of an appointment. The expert
should be reminded that any documentation provided to him is subject
to the rules relating to privilege. 5 As soon as possible after the expert
has been appointed, the solicitor shall explain the client's commercial
and legal objectives in a manner commensurate with the independence
of the expert and prepare for the expert a brief which shall be in a
form appropriate to the nature and complexity of the matter on which
the expert is asked to form an opinion. The Brief will normally contain
the following information:
Details of key documentation and details of location of all relevant
documents. In a straightforward case appropriately bundled documents
should accompany the brief but in a complex case the expert may be required
to review documentation and the brief itself will contain only limited
documentation. 6 On receipt of the brief the solicitor and the expert should review the nature and extent of the brief with regard to the role of the expert and those of any other experts appointed by the solicitor. If the expert has been appointed prior to the solicitor's involvement, it is important that a brief is established jointly. The proliferation of experts should be avoided. The solicitor should be aware that there may be no need to appoint a separate expert in every relevant discipline and that a carefully selected expert may be able to cover more than one area. 7 The solicitor and the expert should keep the brief under review at all times and advise each other of any material changes to relevant issues. The expert should not undertake work outside the brief without the prior approval of the solicitor. 8 The scope of the expert's appointment should be defined and the expert should be appointed in a way that will avoid costs being wasted. 9 The solicitor may wish to discuss with those representing other parties
the matters on which expert opinion is required in order to assist and
refine the brief. 10 The solicitor and the expert shall agree the overall timescale and
the programme within which the expert shall work. If either the solicitor
or the expert becomes aware of any matter likely to affect that time
scale, they should advise the other. The exact timing and sequence will
vary from case to case. Consideration should be given to the extent
of the expert's required attendance at any hearing. These issues should
be discussed at an early stage. 11 The solicitor should keep the expert advised of the time scale set in any litigation or arbitration or of any timetable which is to be met and of any changes that are likely to be made, including in the expected length of or dates of any hearing or trial. 12 The expert when advised of any hearing or trial date on which he is likely to be required to attend or give evidence shall make that date available and inform the solicitor if there are any pre-existing commitments likely to affect the expert's ability to fulfil the appointment. 13 Where the expert has pre-existing commitments the solicitor and
the expert shall work together in order that the interests of the client
can best be served. The expert shall not take on new commitments which
might interfere with his responsibilities under the appointment without
first assessing the position with the solicitor. 14 The report should normally be issued to the solicitor as a draft for discussion and should be accompanied by any documents not originally supplied by the solicitor to the expert. The solicitor and the expert should discuss the format of the report, provided that the report remains the independent product, of the expert. It is wise for the solicitor and the expert to test the expert’s opinions in the light of alternative facts contended for by the client's opponent. 15 When the expert's report has been finalised it will normally be exchanged by the solicitor and not by the expert. Usually simultaneous exchange is appropriate, but in certain cases sequential exchange may be required. The expert and the solicitor should discuss this early in the appointment. The expert's report and any copyright in it will normally be the property of the client. 16 The expert and the solicitor will need to review the status of the
report if the underlying facts change or if the expert's opinion alters. 17 It is common practice for a tribunal to order the parties' expert witnesses to meet to identify those parts of their evidence, which is in issue. There is no standard format for such meetings. What follows is intended as a guide. 18 Meetings of experts should normally take place before exchange of the experts' reports. The predominant view of TeCSA is that, if exchange takes place first, it is more likely that “positions” are taken too early to the detriment of proper discussion at the meeting. 19 The meeting may be most effective if one expert chairs it and an agenda agreed in advance. It may also be of value for the experts to exchange key criteria, which they wish to discuss, for example, Standards or Codes of Practice or methods of valuation. It is appropriate for the parties' solicitors in conjunction with their experts to identify matters in issue in order to determine items for the agenda. Lawyers and clients should not be present at the without prejudice meeting of experts. It is important that the meeting of experts addresses the matters of expert evidence that relate to the matters in issue in the proceedings. The meeting is not the place for the lawyer to “surprise” the other party's expert with a new theory or new documents. 20 Close liaison will be necessary between solicitor and expert and
amongst experts in order to make best use of the meeting. Normally experts
of like discipline will meet together. Occasionally it will be appropriate
to have meetings of experts in more than one discipline, usually following
the initial meeting. For example Architect, Structural Engineer and
Quantity Surveyor, from all parties, might meet to discuss the nature
and extent of remedial works contended for. 21 The expert should report to the solicitor promptly after the meeting and discuss any apparent agreement or narrowing of issues. 22 The expert should, in conjunction with other experts of like discipline, prepare a written note signed by each of them as to matters of opinion on which they are agreed. The note should, where possible, give brief reasons for the views held. It should be remembered that matters of fact are for the tribunal or the agreement of the parties and not matters for the experts to agree between them. Where not all experts can agree a particular point, limited agreements should be explored. 23 If areas of apparent agreement on matters of opinion emerge at a without prejudice meeting, it is good practice to record these promptly to ensure accuracy. It may be appropriate for the expert to reflect on the issues following the meeting. A solicitor should not instruct an expert to apply pressure upon the experts of other parties. 24 The expert does not normally have authority to bind the client,
but the solicitor should make sure that the expert is aware of the extent
of the expert's authority and that matters which the expert agrees in
a note of the meeting may be binding on him. 26 The solicitor shall never impede the expert in reaching agreement
or forming an opinion but can give guidance to the expert in formulating
the note to reflect the matters in issue in the proceedings. 27 The expert shall comply with the requirements of the brief and exercise the reasonable skill and care of a person of the expert's profession, occupation or experience in providing advice on the matters in issue. In giving evidence the expert shall act impartially and owes an overriding duty to the Court or tribunal. 28 The expert shall not express a final concluded opinion until he has considered all relevant issues of fact. The expert will advise the solicitor if the brief appears incomplete or where the expert believes other information is likely to be available. 29 The expert shall advise and assist the solicitor generally, where appropriate, beyond the matters on which the expert is required to give a formal opinion. The expert's report should contain the substance of the expert's evidence that it is intended to give at the tribunal and should be prepared in a clear and succinct manner. The solicitor and the expert should discuss the format of the report. It is not the role of the expert to make a finding of fact, which is in issue. Where an opinion depends upon facts, which are in issue, this should be clearly stated. 30 The solicitor shall throughout the currency of the appointment keep
the expert up to date with information and issues as they relate to
the appointment. The expert shall keep any opinion under review and
have regard to all relevant matters when advising and assisting the
client and the solicitor. After reports have been exchanged the expert
and the solicitor should consider the need for a supplemental report.
31 Fees and terms and conditions should be clearly agreed at the outset
of an appointment. An appropriate breakdown, daily rate and hourly rate
equivalent should be provided. Fees shall be inclusive except where
survey, laboratory or other costs are expressly stated separately. 32 The expert and the solicitor should consider and agree whether the
solicitor appoints the expert and is responsible for the expert's fees,
or whether the solicitor acts as agent for the client by whom all invoices
are to be paid. 33 The expert should normally provide a budget for various stages of any appointment where the work is identifiable. The solicitor and the expert should ensure that fees are proportionate to the value or importance of the matters in issue. 34 It should be made clear and agreed at the outset how regularly fee
invoices are to be rendered, what degree of information they are to
contain and whether they are to be sent to the solicitor or the client.
The expert shall provide supporting information and keep accurate contemporaneous
records sufficient to justify the fees claimed or as may be required
in any taxation of costs or similar procedure. 35 The solicitor should always advise the expert in advance where the
agreement and payment of the expert's fee is subject to the approval
of legal expenses insurers and should immediately notify his expert
of any ceiling on fees. 36 If the expert is appointed in a case where the solicitor's client
has a legal aid certificate in force the solicitor must advise the expert
of the basis on which interim fees can be claimed from the legal aid
fund and whether the expert is to be appointed on the basis that the
expert's fees may be reduced on legal aid taxation. The solicitor shall
advise the expert immediately of any change in the client's legal aid
status. 37 Cancellation charges shall only apply if they have been discussed
and agreed at the outset of the appointment and where the expert can
establish that he has no other appropriate work to undertake. The expert
should not normally charge a minimum or commitment fee. The level of
charge, which may be on a sliding scale, should aim to compensate the
expert for disruption and inefficiency in rearranging his diary at short
notice and not aim to provide remuneration for the whole of the period
cancelled. 38 Where the solicitor has appointed the expert as agent for the client,
the expert may request that the client lodge with the solicitor, or
in a designated account, sufficient monies to provide reasonable security
for the likely fees of the expert. The solicitor and the client will
have regard to the financial status of the client. |
||