Published on Fenwick Elliott (https://www.fenwickelliott.com)

Home > Research & insight > Newsletters > Legal Briefing > Contract issues

Contract issues

27 August 2013 - RWE Npower Renewables Ltd v JN Bentley Ltd

What is the potential relevance of order of precedence provisions when its comes to interpreting apparent ambiguities in contracts?

PDF logoClick to download PDF [1]

18 March 2013 - Aviva Insurance UK Ltd v Hackney Empire Ltd

Did HEL's agreement to make payments to STC "on account" effectively vary the building contract and if so was this prejudicial to Aviva's position such that Aviva was discharged from the bond?

PDF logoClick to download PDF [2]

14 January 2013 - Wuhan Guoyo Logistics Group Co Limited & Others v Emporiki Bank of Greece SA

Was the security document a guarantee or an on-demand bond?

PDF logoClick to download PDF [3]

16 November 2012 - Alstom Power Ltd v Somi Implanti

Did actual title in and property ownership of "Sub-contractor's Equipment" pass to and remain with the main contractor under the terms of the Sub-Contract?

PDF logoClick to download PDF [4]

2 April 2012 - Golden Ocean Group Ltd v (1) Salgaocar Mining Industries PVT Ltd (2) Mr Anil V. Salgaocar

Was a contract of guarantee enforceable where contained not in a single document signed by the guarantor but in a series of documents duly authenticated by the electronic/email signature of the guarantor.

PDF logoClick to download PDF [5]

  • Load more [6]

Links
[1] https://www.fenwickelliott.com/sites/default/files/legal_briefing_11-2013.pdf [2] https://www.fenwickelliott.com/sites/default/files/legal_briefing_04-2013.pdf [3] https://www.fenwickelliott.com/sites/default/files/legal_briefing_01-2013.pdf [4] https://www.fenwickelliott.com/sites/default/files/legal_briefing_19-2012.pdf [5] https://www.fenwickelliott.com/sites/default/files/legal_briefing_09-2012.pdf [6] https://www.fenwickelliott.com/print/research-insight/newsletters/legal-briefing/contract-issues?page=6