Contract issues

27 June 2008 - T & T Fabrications v Hubbard Architectural Metalwork

Was there a contract in writing?

PDF logoClick to download PDF [1]

13 June 2008 – Reinwood Ltd v L Browne & Sons Ltd

What was the effect of the grant of an EOT after the date of issue of the interim certificate but before the final date for payment?

PDF logoClick to download PDF [2]

23 May 2008 - Mair v Arshad

Was the contractual payment mechanism "adequate"?

PDF logoClick to download PDF [3]

16 May 2008 - Tyco Fire & Integrated Solutions v Rolls Royce Motor Cars

Was Tyco liable to Rolls Royce for damage to the project or was the damage covered by the joint names insurance policy provided for by the contract?

PDF logoClick to download PDF [4]

2 May 2008 - Polymers Ltd v Imerys Minerals Ltd

Also the difficulties associated with proving that a product is unfit for purpose if that product has a number of different uses?

PDF logoClick to download PDF [5]

  • Load more [6]

Links
[1] https://www.fenwickelliott.com/sites/default/files/Legal%20Briefing%2025-2008.pdf [2] https://www.fenwickelliott.com/sites/default/files/Legal%20Briefing%2023-2008.pdf [3] https://www.fenwickelliott.com/sites/default/files/Legal%20Briefing%2020-2008.pdf [4] https://www.fenwickelliott.com/sites/default/files/Legal%20Briefing%2019-2008.pdf [5] https://www.fenwickelliott.com/sites/default/files/Legal%20Briefing%2017-2008.pdf [6] https://www.fenwickelliott.com/print/research-insight/newsletters/legal-briefing/contract-issues?page=16