By Philip Hancock, Senior Associate
Last year, I wrote in International Quarterly, Issue 40 [1] about a recent Privy Council decision relating to a FIDIC-based contract and said it was a rare treat (because FIDIC contracts are often considered in confidential arbitrations). Like London buses, another such decision has come in (fairly) quick succession, again relating to a project in Trinidad and Tobago.
This case, Uniform Building Contractors Ltd (Respondent) v The Water and Sewerage Authority of Trinidad and Tobago (Appellant) [2026] UKPC 2, is a helpful discussion of variations and contractor claims under FIDIC contracts. The issues addressed include:
WASA (the Employer) engaged UBC (the Contractor) to design, supply and install 28km of pipeline in Southeast Trinidad and Tobago. The contract was based on the FIDIC Yellow Book (1999 edition – the “Plant and Design-Build Contract”) with bespoke amendments. Disputes arose during the works, and WASA terminated the contracts with UBC. Several years later, UBC started a court claim against WASA, and WASA counterclaimed. At first instance, both UBC’s claims and WASA’s counterclaims were dismissed.
UBC appealed the dismissal of its claims relating to four alleged variations, relating to (i) laying pipework in the roadway, (ii) removal of excavated material unsuitable for use as backfill, (iii) importation of suitable backfill, and (iv) night work (the “Alleged Variations”).
WASA disputed these constituted variations and, if they did, argued that UBC had failed to comply with procedural requirements of the contract, negating UBC’s entitlement to additional payment.
There were almost no contemporaneous documents dealing with how the four Alleged Variations arose. However, the Engineer (appointed by WASA) gave evidence on behalf of UBC, asserting that he considered the four items were variations, and that the Parties had impliedly waived the requirements to comply with the procedural requirements of the Contract in relation to them.
The Court of Appeal of the Republic of Trinidad and Tobago concluded that the first instance judge “was against the weight of the evidence”, relying in particular on the Engineer’s evidence that the Alleged Variations above were variations. The Court of Appeal also indicated that Sub-Clause 20.1 (Contractor’s Claims) did not apply once the contract had been terminated.
Sir Peter Coulson gave the judgment of the Privy Council. The judgment contains very useful guidance on the nature of the FIDIC Yellow Book, and some issues that frequently arise in relation to FIDIC-based contracts.
First, the court dealt with an argument by UBC that the Contract terms should not apply to them, partly because UBC alleged full site investigations had not been possible before the start of the works. The court described that argument as “radical”, that there was “no legal basis for UBC’s attempt at such a comprehensive re-allocation of risk and reward as between the parties”, and rejected it.
The court explained that under the FIDIC Yellow Book the Contractor is responsible for the design and construction of the works. It is a lump sum contract, and the Contractor is taken to have allowed for all foreseeable risks in the Contractor’s rates: “[The Yellow Book] is designed to provide as much financial certainty as possible for both sides”.
Second, the Privy Council noted the Court of Appeal did not address the terms of the Contract but instead determined the Alleged Variations were Variations because they were so considered by the Engineer.
The Privy Council explained that “the question whether one or more of the four disputed items is or is not a variation is a function of the contract terms” [emphasis added]. To determine whether there has been a Variation under the Contract, one needs to look at how “Variation” is defined. Under the FIDIC Yellow Book, it is “any change to the Employer’s Requirements or the Works…” (Sub-Clause 1.1.6.9). So, one must determine the scope of the Employer’s Requirements and Works, and whether the Alleged Variations are within that scope, or additional to it.
The Privy Council considered that all four of the Alleged Variations were part of the Works. On proper analysis of the Employer’s Requirements and other Contract documents, the Alleged Variations were (or should have been) in the contemplation of UBC, and so within the fixed lump sum price. The court relied on several provisions (including certain bespoke terms), which supported the premise that the Yellow Book transfers full design and build responsibility to the Contractor.
Third, the Privy Council explored the contractual process for Variations and effectively concluded that none of the contractual process had been followed by either party (not an uncommon situation!). Broadly, the process entails an instruction, or request for proposal, initiated by the Engineer, ultimately leading to a determination by the Engineer under Sub-Clause 3.5 (Determinations) of the Contractor’s entitlement to additional payment.
Importantly, the court explored the relevance of Sub-Clause 20.1 (Contractor’s Claims) to Variations. This was a situation where there had been no engagement by the Engineer in relation to the Alleged Variations; there had been no notice or request under Sub-Clause 13.1 (Right to Vary), nor any determination under Sub-Clause 3.5. In the circumstances, if UBC wanted additional payment, it was necessary to submit a claim under Sub-Clause 20.1.
Sub-Clause 20.1 directs that the Contractor must submit a notice of claim “as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or circumstance [giving rise to the claim]”. If the Contractor fails to do so, the Sub-Clause expressly states that the Contractor loses its entitlement to an extension of time/additional payment. On this point, the judge also cited a book co-authored by my colleague Jeremy Glover (together with Simon Hughes KC) on this point – Understanding the FIDIC Red and Yellow Books, 3rd Edition – confirming that the Sub-Clause 20.1 notice of claim is treated as a condition precedent and failure to comply can provide a counterparty a complete defence to the claim.
The Privy Council found that UBC’s failure to submit a Sub-Clause 20.1 notice of claim was “fatal” to its claim.
The Privy Council also found that, because the claim regarding the Alleged Variations arose prior to termination of the Contract, Sub-Clause 20.1 applied (thereby rejecting the Court of Appeal’s finding that Sub-Clause 20.1 did not apply due to the termination).
UBC argued that it was entitled to additional payment partly because to find otherwise would be unfair, in circumstances that the Engineer agreed the Alleged Variations were Variations, and WASA had the benefit of the additional work. UBC relied on arguments including waiver and estoppel.
The Privy Council disagreed with UBC. Their key conclusions included that:
This might seem to some quite a harsh result, given the Engineer considered the Alleged Variations were indeed variations. However, it is a useful reminder that one must first understand the original scope of Works to determine if there has been a variation to them. It is also important to follow the processes and procedures under the Contract, at the time particular issues arise, so that parties do not lose their entitlement over a procedural non-compliance.
Previous article [2] | Next article [3]
Links
[1] https://www.fenwickelliott.com/research-insight/newsletters/international-quarterly/fidic-termination-for-convenience-payment
[2] https://www.fenwickelliott.com/research-insight/newsletters/international-quarterly/construction-amid-war-and-hostilities-the-principal-issues-under-fidic
[3] https://www.fenwickelliott.com/research-insight/newsletters/international-quarterly/the-new-uae-civil-code