Gurney Consulting Engineers v Pearson Pension Property Fund Ltd & Anr

Issue 51 - September 2004

Had a contract had been concluded between the parties such that it incorporated the standard ACE conditions of engagement? More specifically was there a valid arbitration agreement?

PDF logoClick to download PDF [1]

Mowlem Plc v Phi Group Ltd

Issue 51 - September 2004

Where a party made a request for the supply of material, was there an agreement to pay a reasonable price for that material?

PDF logoClick to download PDF [1]

BP Exploration Operating Co Ltd v Kvaerner Oil Field Products Ltd

Issue 48 - June 2004

What is the extent of cover offered by a contractor's all-risks insurance policy.

PDF logoClick to download PDF [2]

Bath & North East Somerset DC v Mowlem plc

Issue 45 - March 2004

Where a contractor refused to carry out an instruction from an employer, was that contractor able to deny access to a second contractor appointed to carry out the work?

PDF logoClick to download PDF [3]

JDM Accord Ltd v Secretary of State for the Environment, Food and Rural Affairs

Issue 44 - February 2004

His Honour Judge Thornton QC provides guidance on what factors should be taken into account when placing weight on timesheets to back up a claim for fees.

PDF logoClick to download PDF [4]

  • Load more [5]

Links
[1] https://www.fenwickelliott.com/sites/default/files/docs/dispatch/Dispatch_issue_51.pdf [2] https://www.fenwickelliott.com/sites/default/files/docs/dispatch/Dispatch_issue_48.pdf [3] https://www.fenwickelliott.com/sites/default/files/docs/dispatch/Dispatch_issue_45.pdf [4] https://www.fenwickelliott.com/sites/default/files/docs/dispatch/Dispatch_issue_44.pdf [5] https://www.fenwickelliott.com/print/research-insight/newsletters/dispatch/contract-issues?page=41