City Inn Ltd v Shepherd Construction Ltd - Part 2

Issue 123 - September 2010

Did the employer waive the right to rely upon the contractor's failure to comply with the strict notice requirements of the contract?

PDF logoClick to download PDF [1]

City Inn Ltd v Shepherd Construction Ltd

Issue 122 - August 2010

Where there is true concurrency, is it ever appropriate to apportion responsibility for the delay between the two competing causes?

PDF logoClick to download PDF [2]

WW Gear Construction Ltd v McGee Group Ltd

Issue 121 - July 2010

Was the submission of a timely application a condition precedent to the allowance to the contractor of loss or expense?

PDF logoClick to download PDF [3]

Kookmin Bank v Rainy Sky SA & Others

Issue 120 - June 2010

What do the words "all such sums due under the Contract" mean when found in a Bond? Decision of Court of Appeal over-turned. See Issue 138 [4].

PDF logoClick to download PDF [5]

Gold Group Properties Ltd v BDW Trading Ltd

Issue 118 - April 2010

Might the fall in the property prices enable a party to claim that a contract was frustrated?

PDF logoClick to download PDF [6]

  • Load more [7]

Links
[1] https://www.fenwickelliott.com/sites/default/files/Dispatch_issue_123.pdf [2] https://www.fenwickelliott.com/sites/default/files/Dispatch_issue_122.pdf [3] https://www.fenwickelliott.com/sites/default/files/Dispatch_issue_121.pdf [4] https://www.fenwickelliott.com/sites/default/files/dispatch_issue_138.pdf [5] https://www.fenwickelliott.com/sites/default/files/Dispatch_issue_120.pdf [6] https://www.fenwickelliott.com/sites/default/files/Dispatch_issue_118.pdf [7] https://www.fenwickelliott.com/print/research-insight/newsletters/dispatch/contract-issues?page=32